Ongoing Roadworks
Yalinda Drive, Woods Road and Brockway Drive
3 December 2024
- New Yalinda Drive bridge open
- Woods Road and Brockway Drive connected via a new roundabout
- A portion of Brockway Drive will open 6 December. During this time, a detour will be in place via Woods Road, Jilley Road and Manea Drive.
- Map
- Travel Map
Banksia Road, Gelorup
3 December 2024
- Intersection closure at Banksia Road and Bussell Highway
- Detours in place
- Map
- Travel Map
Raymond Road and Treendale Road
28 November 2024
- Westbound traffic on Raymond Road will switch on to a portion of the new alignment
- From early December, the new connection from Raymond Road to the existing Treendale Road will open
- Traffic management will remain in place until 14 December to enable kerbing and hard landscaping works to occur.
- There will be short term intervals where traffic may operate in a single lane configuration on either side of the carriageway managed by traffic controllers.
- Map
- Travel Map
Allenville Road, Gelorup
25 November to 16 December 2024
- Temporary road closure on Allenville Road.
- Detour will be in place via Hasties Road, Jules Road and a new section of Lillydale Road.
- Heavy vehicles will be required to detour via Hasties Road, Bussell Highway, Robertson Drive and South Western Highway. For more information, please visit HVS Network Map.
- Map
- Travel Map
Travelling on South Western Highway (south) near Lillydale Road and the Bunbury Outer Ring Road
20 November until December 2024
- Willinge Drive opening from Timber Road to South Western Highway
- Temporary closure of South Western Highway (south) between Willinge Drive and the Bunbury Outer Ring Road
- Detours via Willinge Drive and the Bunbury Outer Ring Road
- Map
- Travel Map
Travelling on South Western Highway (south) - out of hours works
7pm to 7am - 21 to 24 November 2024
- Detours via Robertson Drive and South Western Highway (north) and Willinge Drive
- Map
- Travel Map
Existing Bunbury Outer Ring Road (BORR) and Willinge Drive roundabout
14 November to 25 November 2024
- Turning restrictions on the BORR and Willinge roundabout
- Access changes to Timber Road and BORR westbound
- Map
- Travel Map
Clifton Road, Australind
14 November to December 2024
- Closure of existing Clifton Road (to be renamed Tilbury Close) intersection with Forrest Highway
- Detour via Grand Entrance, The Promenade and Paris Road in place until mid-December
- Map
- Travel Map
Existing Bunbury Outer Ring Road (BORR) and Moore Road, Davenport
11 November to 9 December 2024
- Temporary closure of the existing BORR between Willinge Drive and Boyanup-Picton Road.
- Temporary closure Moore Road between BORR and Kowal Avenue.
- Detours via Willinge Drive and Boyanup Picton Road
- Map
- Travel Map
Moore Road, Davenport
9 December 2024
- Permanent intersection closure of Moore Road and the existing Bunbury Outer Ring Road
- The new alignment of Moore Road open
- Map
- Travel Map
Paris Road and Clifton Road, Australind
15 October to December 2024
- Paris Road and Clifton Road connected over the bridge via the new interchange.
- Northbound traffic on Forrest Highway will be switched on to the permanent alignment which will use the new intersection with Paris Road and Clifton Road.
- Future intersection closure of Clifton Road and Forrest Highwy
- Paris Road and Clifton Road Connection Map
- Future Closure Map
- Travel Map
South Western Highway and Discovery Road, Waterloo
18 September to December 2024
- Temporary closures of South Western Highway and Discovery Road
- South Western Highway will be diverted on to a temporary alignment via the new Discovery Road and existing Waterloo Road.
- Single lane closures, managed by 24/7 automated timed traffic signals.
- Access to South Western Highway will be via Martin-Pelusey Road and Brysinda Road.
- Map
- Travel Map
Lillydale Road (previously Centenary Road)
1 August to November 2024
- Left in, left out access onto Bussell Highway
- Map
- Travel Map
Yalinda Drive and Cokelup Road
31 July to late - September 2024
- 24/7 automated traffic signals
- Reduced speedlimits (40 km/h) in place
- Map
- Travel Map
Lillydale Road between Queelup Road and South Western Highway
22 August 2024 to late-October 2024
- Temporary road closure on Lillydale Road.
- Traffic switched onto new alignment on South Western Highway
- Detours in place along the Bunbury Outer Ring Road.
- Map
- Travel Map
Travelling on Bussell Highway from Gelorup Rise to Grevillea Road
Early June 2024 until December 2024
- Bussell Highway switched to a new alignment. One lane operational in each direction.
- Calinup Road will be re-aligned onto the new Grevillea Road.
- Access to Grevillea Road from Calinup Road will be via single lane configuration that will be managed by temporary automatic traffic signals operating 24/7.
- A portion of Calinup Road where it meets Bussell Highway, will be permanently closed.
- Banksia Road (previously Woods Road) remains a left in, left out arrangement
- Map
- Travel Map
Martin-Pelusey Road and Golding Crescent
4 December 2023 to December 2024 - 24/7 closure
- Road closure
- Golding Crescent temporarily closed between Nicholson Road and Martin-Pelusey Road
- Please note – until June 2024, Martin-Pelusey Road will be temporarily closed between Harris Road, Copplestone Road and South Western Highway.
- Travel Map
Bussell Highway near Lillydale Road (previously Centenary Road)
30 April 2024 to November 2024
- Traffic is shifted onto a temporary road layout, with two lanes open in both directions
- Reduced speed limits (60 km/h) in place
- Pedestrians and cyclists continue to use existing shared path
- Travel Map
Woods Road, Eucalypt Drive and Yalinda Drive
17 April 2023 to November 2024
- Road closure
- Temporary road closures
- Detours in place via Gelorup Rise and Calinup Road
- Travel Map
Introducing ‘Transition’ – the latest artwork to be unveiled on the Wilman Wadandi Highway
Designed and painted by Kyle Hughes-Odgers, the screen walls on the northern side of the mega-bridge will feature a unique design which ties into the project’s Urban Design strategy.
Discover the Wilman Wadandi Highway
Safer, easier and more reliable trips through the South West are almost here.
Future builders: school students step into the world of construction
In September, the team held three events with various schools and welcomed over 30 kids onsite, giving students the opportunity to see the region’s biggest road infrastructure project and have a hands-on experience learning about the construction industry.
Engineering on the wild side - Gelorup fauna land bridge taking shape
Significant progress is continuing on the Gelorup Fauna Land Bridge, one of 12 bridges being built as part of the Wilman Wadandi Highway (Bunbury Outer Ring Road Project). This bridge, designed to support the wildlife crossing and assist in maintaining local biodiversity, is unique due to its features in both construction methods and design choices.