Bunbury Outer Ring Road

Under constructionUnder Construction

A 27-kilometre four-lane, high standard road linking Forrest Highway to Bussell Highway. The project will ease congestion and provide safer, more efficient traffic routes for freight, tourists, and locals. Banner photo: Yaka Dandjoo graduates, plus Kat Jones working on BORR

Yaka Dandjoo graduates, plus Kat Jones working on BORR

What's Happening

 Out of Hours Works – Bussell Highway Interchange Bridge

In mid-July there will be an early morning concrete pour to build the deck of the Bussell Highway interchange bridge. This concrete pour is one of the most technical concreting activities on the project as it involves the simultaneous pouring of the bridge deck and the stitch areas that connect the deck to the bridge abutments. Due to the volume of concrete required and to meet quality requirements, works are expected to commence from 3.30am and will continue into the working day.

During the works you may notice an increase in noise from the concrete pumps operating and trucks arriving and departing site. All works are conducted with approval from the Shire of Capel and in accordance with an out-of-hours management plan.

Some traffic management will also be required on Bussell Highway until 7am to enable the concrete trucks to access and depart the site safely. If you have any concerns during this work, please call 138 138, which is a 24/7 number.

 Check out our latest Southern Section Construction Update.

 Community Hub closure

On Friday 21 June, the BORR Community Hub permanently closed. Over the past three years, we have welcomed 2,200 visitors and met many members of the Bunbury community.

Even though the Hub is no longer open, our team is still here to assist you. For any questions about our projects, please reach out to us via email on enquiries@mainroads.wa.gov.au or via phone on 138 138.

Roadworks

Ongoing Roadworks

Yalinda Drive and Cokelup Road
31 July to late - August 2024
  • 24/7 automated traffic signals
  • Reduced speedlimits (40 km/h) in place
  • Map
  • Travel Map
Treendale Road, Roelands
From February to September 2024
  • Temporary partial road closure
  • Detours on Ranson Drive
  • Map
  • Travel Map
Calinup and Grevillea Road
July to mid-August 2024
  • 7am – 7pm Monday to Saturday
  • Stop/start traffic on Grevillea Road to enable trucks to transport sand across the road.
  • Speed reduction to 40km/hr
  • The crossing point is located east of the Grevillea Road Bussell Highway intersection.
Discovery Road Opening
23 April to December 2024
  • Opening of the new Discovery Road.
  • Permanent closure of a portion of Waterloo Road
  • Intermittent lane closures and traffic management in place until December 2024
  • Access to the northern portion of Wireless Road will remain from South Western Highway
  • Map
  • Travel Map

Travelling on Bussell Highway from Gelorup Rise to Grevillea Road
Early June 2024 until December 2024

  • Bussell Highway switched to a new alignment. One lane operational in each direction.
  • Calinup Road will be re-aligned onto the new Grevillea Road.
  • Access to Grevillea Road from Calinup Road will be via single lane configuration that will be managed by temporary automatic traffic signals operating 24/7.
  • A portion of Calinup Road where it meets Bussell Highway, will be permanently closed.
  • Banksia Road (previously Woods Road) remains a left in, left out arrangement
  • Map
  • Travel Map
Brysinda Road opening
19 June 2024
  • Opening of Brysinda Road
  • Map
  • New east-west local connection between Martin-Pelusey Road and Discovery Road.
  • Intermittent lane closures and traffic management will be in place when required for Brysinda Road and Martin-Pelusey Road finishing works.
  • Travel Map 

Harris Road permanent closure
19 June 2024

  • Permanent closure of a portion of Harris Road
  • Harris Road east from Martin-Pelusey Road will be open for local access only.
  • Travel Map 

Martin-Pelusey Road and Golding Crescent
4 December 2023 to December 2024 -24/7 closure

  • Road closure
  • Golding Crescent temporarily closed between Nicholson Road and Martin-Pelusey Road
  • Please note – until June 2024, Martin-Pelusey Road will be temporarily closed between Harris Road, Copplestone Road and South Western Highway.
  • Travel Map

Clifton Road, Australind
July to November 2024

  • Modified road layout and intersection at Howson Drive
  • Map

Bussell Highway near Lillydale Road (previously Centenary Road)
30 April 2024 to November 2024

  • Traffic is shifted onto a temporary road layout, with two lanes open in both directions
  • Reduced speed limits (60 km/h) in place
  • Pedestrians and cyclists continue to use existing shared path
  • Travel Map

Woods Road, Eucalypt Drive and Yalinda Drive
17 April 2023 to 31 October 2024 - 7am to 5pm

  • Road closure
  • Temporary road closures 
  • Detours in place via Gelorup Rise and Calinup Road
  • Travel Map
Travelling on South Western Highway near Waterloo Road
From 24 January 2024 to October 2024 
  • Traffic shifted onto temporary lane road layout
  • Reduced speed limits in place
  • Map
  • Travel map 

Travelling on Forrest Highway near Paris Road and Clifton Road
12 September 2023 until October 2024

  • Reduced speed limits in place
  • Traffic shifted onto temporary lane road layout:
  • Southbound traffic on Forrest Highway will be shifted onto temporary lanes 
  • Northbound traffic on Forrest Highway will be shifted onto temporary lanes (From October)

Moore Road, Davenport
July to September 2024

  • New connection to Boyanup-Picton Rd
  • Automated traffic signals operational 24/7
  • Map
  • Travel Map

Bunbury Outer Ring Road between Moore Road and Boyanup-Picton Road
July to September 2024

  • Temporary closure between Moore Road and Boyanup-Picton Road.
  • The Bunbury Outer Ring Road between Willinge Drive and Moore Road will operate in a single lane in each direction.
  • Map
  • Travel Map

Travelling on Allenville Road and Lillydale Road in Gelorup
July to October 2024

  • Traffic Shifted onto new road layout 
  • Reduced speed limits in place
  • Single lane closure in place
  • Map
  • Travel Map

Travelling on South Western Highway (south) near Lillydale Road
29 February until July 2024

  • 7pm to 7am
  • Traffic shifted onto temporary lanes
  • Reduced speed limits in place
  • Map 
  • Travel Map

Paris Road between Forrest Highway and the entrance to Spud Shed
From June to October 2024 - 24/7 works

  • Road closure
  • Temporary road closure
  • Detours in place along The Promenade, Kingston Drive and Grand Entrance
  • Travel Map

Raymond Road
Ongoing

  • Temporary traffic diversion on Raymond Road
  • Reduced speed limit to 40 km/h
  • Map
  • Travel Map
See more projects news »
Plantings Take Root At Raymond Road

Plantings Take Root At Raymond Road

A range of native species were planted at the Raymond Road site on the Bunbury Outer Ring Road (BORR). In fact, 50,000 individual plants comprising of over 50 different native species were planted from the area north of Raymond Road down to Collie River.

Bussell Highway Y-interchange Beam Installation is Complete

Bussell Highway Y-interchange Beam Installation is Complete

Bridge building continues on the Bunbury Outer Ring Road (BORR) project with the recent completion of the beam installation at the BORR-Bussell Highway Y-interchange.

It’s Back to School On BORR

It’s Back to School On BORR

The Bunbury Outer Ring Road (BORR) project, with its vast size and scope, has created unique opportunities to engage local schools and students.

The Preston River Bridge Now Has Beams!

The Preston River Bridge Now Has Beams!

The Preston River bridge on the Willinge Drive extension, as part of the Bunbury Outer Ring Road (BORR) project, has reached its next milestone with the beams now installed and in place. But what does it take to get super-long bridge beams craned into place over a river?

See more projects news »

Planning & Alignment

Flora, Fauna and Environment

Native plants

Environment

Learn more »
Bright and colorful Aboriginal artwork

Aboriginal Engagement

Learn more »
27 km

key transport corridor

Safer

local roads

Improved

traffic flow

Page last reviewed:  | Last updated: 

Acknowledgement of country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback