Swan River Crossings Fremantle

Under constructionUnder Construction

Building Fremantle’s new traffic bridge to improve journeys for all road and river users.

Swan River Crossings <em>Fremantle</em>

What’s happening

New concrete deck complete

Concrete deck pours for the new bridge are complete, and road barrier installation is almost finished. Parapet installation is progressing well, with 185 of 192 units now in place and all four bridge  towers are visible with scaffolding fully removed.

Navigation for vessels has been made easier with most of the underwater piles now removed from the river.  The two temporary jetties on the western side of the bridge have been removed, with the eastern jetties and cranes expected to be off‑site by August.

Terraced retaining walls on the south‑eastern side of the bridge are almost 80% complete, and staircase construction is underway. The new road connection to Swan Street on the northern side of the bridge is making strong progress and is supported by 13,000 cubic metres of imported sand – that’s approximately 800 truckloads.

Fun Fact

Some concrete pours were completed using a unique method where a 36-metre concrete boom truck (weighing approximately 24 tonnes) was lifted onto the bridge deck to place the concrete. This method is not usually used in Australia - particularly on bridges!

Bridge now closed - rethink the way you travel

The Fremantle Traffic Bridge is now closed to traffic while we complete major works, including removing the old bridge, installing the new bridge deck and building the new road. While the closure is for up to 12 months, the construction schedule will be reviewed and the program expedited where possible.

Transport options during bridge closure

The State Government has announced a series of measures to make it easier for people to consider alternative modes of travel during bridge closure. These include:

  • Additional train and bus services.
  • Additional free parking bays for SmartRider users.
  • Cheaper public transport, through the introduction of the new flat fare.

For more information, please view our latest Fact Sheet. These measures have also been informed by consultation with local primary and secondary schools, other key stakeholders and the wider community.

Public Transport

The Public Transport Authority (PTA) has created a dedicated webpage with information about public transport changes during closure, including maps and timetables. Please visit the Fremantle Traffic Bridge Closure webpage for more details  

Pedestrians and Cyclists

WestCycle has created a webpage with key information (including wayfinding) for pedestrians and cyclists specifically during the closure. Please visit the Fremantle Traffic Bridge Closure webpage for more information.

How you can help

We strongly encourage road users to examine how and when they travel through the area. This includes consideration of public transport, travelling outside of peak, examining your choice of route and travel patterns, and talking to work colleagues about flexible work arrangements and carpooling.

Every car journey saved will help keep Fremantle moving and reduce delays on Stirling Highway.

Road Network changes to support bridge closure

Traffic modelling shows that the closure of the bridge will have a severe impact on the road network with commuters likely to experience delays. As a result, some temporary network modifications are essential to keep traffic moving during the closure. 

The proposed changes are explained in detail in our Road Network Changes Fact Sheet and our interactive map below.

All changes will be in place from 1 February 2026 until completion of the project.

Road Network Changes - Frequently Asked Questions

River restrictions for temporary jetty removal - April-September 2026

Temporary jetties used during construction will need to be removed in coming months. This requires in-river vibratory piling to extract the temporary piles. This process will generate noise, which will be amplified underwater.

Removal of the temporary jetties is expected to commence in April 2026 and continue intermittently to September 2026. Most works will occur between 7am and 7pm from Monday to Saturday.

Restrictions are needed to ensure members of the public and pets are not exposed to heightened levels of underwater noise, including:

  • Swimmers and passive craft users will not be able to access the water for activities between the Port to east of the Fremantle Traffic Bridge. Prohibited recreational activities include:
    • Swimming
    • Snorkelling
    • Scuba Diving
    • Dogs in Water
    • Passive Craft:
      • Stand-Up Paddle
      • Kayaking
      • Rowing
      • Hydrofoil
      • Other watercraft, including inflatables.
Swan River Crossings river restrictions map
Click image to enlarge

 

 

SRC Key Features of the new bridge

Page last reviewed:  | Last updated: 

Acknowledgement of Country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback