Mandurah Estuary Bridge Duplication

Mandurah Road

Under constructionUnder Construction

Construction of a second bridge alongside Mandurah Estuary Bridge.

Mandurah Bridge over river surrounded by trees

What's happening

 Preparing the casting bed

Works in the casting bed area adjacent to Waterlily Drive continues as we pour concrete foundations, pedestals and construct crane pads. Concrete pours for the casting bed will continue in July as we prepare to cast the large bridge segments that we will start launching across the estuary from early September.

Where possible, we will carry out the majority of works during normal working hours. However, some concrete pours will need to start in the early hours of the morning, even earlier during the summer months, so that the finished concrete complies with structural conformance requirements. The casting yard will remain operational until mid to late 2025.

 Piling continues

The construction team will continue with land-based piling in July along with piling for the new fishing platform.

This work will be done from the reclaimed area on the eastern foreshore, using a land-based piling rig. Marine piling will get underway in August with the start of work on the five water-based piers.

Mandurah Estuary Bridge - Piling continues - July 24

 Wildlife and heritage monitoring

Marine Mammal Observers (MMOs) will be in position to monitor dolphin activity and where necessary follow the appropriate controls to ensure all dolphins and other marine wildlife are not adversely impacted during activities in the estuary. Heritage monitors are also engaged for any disturbance works in specific heritage sites, including areas in the estuary.

During all piling works, residents living close to the project and surrounding area may expect loud noise and vibrations which are common with these works, this will be intermittently ongoing until mid-November 2024

 
 Limestone retaining walls

Limestone retaining walls adjacent to Seahawk Drive and Waterside Drive, and those adjacent to Leisure Way will be constructed from July.

Nearby residents are reminded that as part of the construction process, we need to lower the groundwater level to facilitate the construction of the walls. Water will be extracted from the ground and pumped into nearby limestone holding basins.

 Read more about what’s coming up in the July Construction Update.

Path closures and access impacts
Closure of the cycle access path from Waterside Drive to Mandurah Road for the remainder of the project.

Friday 7 June until late 2025

As the project is progressing, we now need to place temporary barriers along the road which will block off the access path. We will also be shortly commencing works to construct retaining limestone walls that will support future noise walls along Waterside Drive.

There is also no access to and from Waterlily Drive to Mandurah Road for the duration of the project.

Cyclists, mobility devise users and pedestrians need to use the detour route identified to Leslie Street and cross Mandurah Road at this intersection.

The cycle access path will be reinstated aligning with new median and access path to Waterlily Drive at the end of the project.

Better

connectivity & safety

Improve

traffic flow

Page last reviewed:  | Last updated: 

Acknowledgement of country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback