What's happening
Road construction is continuing where weather conditions are favourable.
The intersection of Sues Road and Bussell Highway has been reopened under temporary traffic management, with the right turn into Sues Road remaining closed. A detour will be available via Vasse Highway during this closure.
Periods of closures to the side roads impacted by the project will be required over the coming months, to facilitate tie ins of the local road network to the new dual carriageway. Appropriate detours will be in place during these times.
Visit our Travel Map for more information.
For the safety of all road users and road workers in the area, please follow detour signage and obey traffic management when travelling through the area. Plan ahead to avoid traffic delays.
Project Status
- Stage One of the project, the 5-kilometre section between Capel and Hutton Road, was completed in December 2021.
- The first section of Stage Two, 3.3 kilometres between Hutton Road and north of Ludlow River, was completed in April 2022.
- Construction of the remaining section of Stage Two, between Ludlow River and Sabina, is currently scheduled for completion in early 2025.
Ludlow River to Ruabon Road Section
- The Ludlow River bridge structure and major culvert on Ludlow-Hithergreen Road are complete.
- Earthworks to the new carriageway are complete and pavement construction is nearing completion.
- Construction of temporary works to switch traffic onto a 4-kilometre section of new southbound carriageway is in progress, to enable works on the existing (northbound) carriageway to commence.
Ruabon Road to Abba River Section
- Earthworks to the new carriageway have been completed, with pavement works nearing completion.
- Earthworks and pavement works on Layman Road are complete.
- Earthworks on Wonnerup Road are complete, with pavement works to commence in the next few weeks.
- The Abba River bridge structure is complete, with pavement works to the bridge approaches in progress.
Abba River to Sabina Section
- The majority of the new carriageway has been completed and sealed to the north of Sues Road.
- Construction of the pavement at the new Sues Road roundabout is continuing, with some sections sealed to facilitate a temporary intersection layout.
- The Sabina River bridge structure is complete, with pavement works to the bridge approaches in progress.
Stage One: Construction of a 5-kilometre second carriageway from just south of Spurr Street to Hutton Road; including reconstruction of part of the existing carriageway.
Stage Two: Construction of a second carriageway over a 12-kilometre section between Hutton Road and Busselton; including construction of three bridges over the Abba, Ludlow and Sabina River. The works also include reconstruction of parts of the existing carriageway and construction of a dual lane roundabout at the intersection of Bussell Highway and Sues Road.