BORR reaches 50 per cent completion

The Bunbury Outer Ring Road (BORR) has reached a key milestone of 50 per cent completion!

Published: 03 August 2023, Updated: 11 August 2023

Rolling Milestones Aren’t Gathering Moss on BORR

The Bunbury Outer Ring Road’s (BORR) milestone of being 50% complete is now behind us and we’re entering an exciting new phase of construction!

The transformational project that is BORR may be a giant project, but it’s starting to come together! The month of July saw the project reach a 51.5% completion rate.

That means, of course, that BORR is more than halfway completed.

For those eagle-eyed construction enthusiasts, some of the most recent achievements that has helped the team reach this achievement include:

  • Delivery of imported materials ahead of the original schedule.
  • 47 beams cast to date in a local facility.
  • Completion of foundation treatments along the Discovery Road intersection.
  • Bridge beams installed on both the Raymond Road and South West Highway bridges.
  • Deck pour completed on the Raymond Road bridge.

 Make sure to watch the video to see how far BORR has come.

Back to Project News

Page last reviewed:  | Last updated: 

Acknowledgement of country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback