What's Happening
Early work has commenced:
- Survey, services locations, geotechnical investigations, and traffic modelling is complete.
- Preliminary road design is complete.
- Flood modelling and drainage design is complete.
- Environmental and heritage surveys are complete.
Project development continues with:
- Land acquisition.
- Detailed road design.
- Service provider asset relocation designs.
- Forrest Highway southern verge drainage channel retaining wall design, and
- Stakeholder engagement.
Preconstruction work (including fencing, services relocations, drainage channel and property access) is due to commence late 2024/early 2025.