Lloyd Street Extension

Under constructionUnder Construction

Completion of Lloyd Street between Great Eastern Highway and the Great Eastern Highway Bypass, including a new bridge over Helena River.

Lloyd Street Extension render

What's happening

Pre-construction works update – November 2026

Early site works are ongoing in readiness for construction of the Lloyd Street Bridge over the Helena River. Site investigations were completed in October, providing valuable information about ground conditions to inform the bridge design and construction planning. Meanwhile, the project’s main construction compound is nearing completion, ready for the team to move in before the end of the year.

In December, the team will prepare the bridge site for major works to commence in the new year. This includes vegetation removal, installation of boundary fencing and minor earthworks. While some trees and native vegetation need to be removed to construct the bridge, the project has been designed to minimise clearing as much as possible. The final bridge design reduces vegetation clearing by approximately 20 per cent compared with the previous design.

Site activity will ramp up in early 2027, starting with earthworks to establish piling pads, followed by construction of the piers that will eventually support the bridge deck.

Please view our latest Pre-construction Works Update for more information.

Lloyd Street Bridge a step closer following design agreement with Traditional Owners

The Lloyd Street Bridge is a step closer to construction following agreement on design principles with local Traditional Owners.

The agreement follows four years of consultation, collaboration and design investigation to ensure the crossing avoids impact to cultural significant sites, including the Helena River and a seasonal pool located on the bridge’s alignment.

The new design features a 180m long bridge, spanning most of the Helena River floodplain. Two sets of supporting piers will be positioned away from culturally sensitive areas. The new design also significantly reduces the project’s footprint, reducing the vegetation clearing requirement by around 20 per cent. The bridge will have two lanes in each direction, as well as shared paths for pedestrians and cyclists.

With key design principles agreed, the project will proceed to the detailed design stage. This will be accompanied by site investigations and broader communication and stakeholder engagement.

Please view the latest State Government Media Statement for more information.

Improve

safety

Reduced

congestion

Better

access to Midland and Hazelmere

Page last reviewed:  | Last updated: 

Acknowledgement of Country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback