Bussell Highway Y-interchange Beam Installation is Complete

Bridge building continues on the Bunbury Outer Ring Road (BORR) project with the recent completion of the beam installation at the BORR-Bussell Highway Y-interchange.

Published: 16 July 2024, Updated: 16 July 2024

The BORR-Bussell Highway bridge sits at the southern end of the BORR alignment forms part of an innovatively designed interchange in the shape of a Y.

Due to this configuration, the interchange design had to meet some unique requirements to accommodate the curve of the BORR alignment. So, an equally unique bridge beam design had to be incorporated.

The bridge is on a high skew of 41.5 degrees – meaning that the angle between the bridge structure itself, and the road below, is not perpendicular. This ensures a smoother and more continuous transition on and off the bridge for vehicles without the need for sharp turns.

To achieve this design, a project-first continuous beam design needed to be used with specific construction considerations taken into account.

The Design: Continuous Beams

Using a continuous beam design means that the beams extend continuously over multiple supports. This is as opposed to simply being supported at each end of the bridge. Multiple supports help with load distribution and structural efficiency of a ‘skewed bridge’, increasing carrying capacity and strength.

Each of the eight beams weigh 145 tons and are 35 metres long.


BORR 160724 - Beam install happening at the Y interchange
 Beam installation in progress onsite

The Construction: Beam Installation

One side of each beam was installed on the abutments (i.e., the ends of the bridge span) and the other side supported by temporary structures. Then a stitch pour took place to connect the various precast concrete segments of the bridge and lock each beam to the span next to it. When completed, the beams will have the permanent support they need, and the temporary support structures can be removed.

To achieve this for all eight beams, an LTM1750 crane—which is a 750-ton mobile telescopic crane for extra strength and reach—was used. It took five days for the beam installation to be completed but now that it has, the BORR-Bussell Highway bridge is ready for the next stage in its construction: deck formwork and concrete pour!

Back to Project News

Page last reviewed:  | Last updated: 

Acknowledgement of country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback