Temporary Works to Make a Permanent Difference at Collie River Bridge
There are a lot of considerations and a significant amount of planning that goes into bridge building on the Bunbury Outer Ring Road (BORR) … and the bridge at Collie River is no different.
Published: 13 February 2024, Updated: 13 February 2024
In fact, the bridge at Collie River is not one bridge, but two separate bridges to facilitate the flow of traffic in either direction.
Before the construction of the piles for either bridge could begin, the slopes of the riverbank had to be reinforced to ensure that the piling rigs had a safe and stable ground to operate from. Additionally, it was crucial that the natural environment was protected whilst constructing the bridges.
The temporary works used to reinforce the bank considered the impact of slope stability and erosion and were consciously designed to prevent both through a variety of unique controls.
Temporary works are the various structures, supports and systems that are employed temporarily to help facilitate construction. Once the permanent structures are in place, the temporary works can be removed.
For the Collie River bridges, a variety of temporary works were required and applied in accordance with the necessary environmental permits and approvals. These included:
- A silt curtain to act as a protective barrier for the river and to prevent sediment, silt and soil entering the watercourse.
- A sediment fence to provide further protection for the river by retaining sediment, silt and soil while also allowing water to drain into the river, reducing the impact on aquatic fauna.
- Use of geofabric - a unique high-strength material specifically designed to stabilise soil and keep earth in place.
- Bulk-A-Bags: large, custom designed bags filled with clean aggregate to provide the necessary weight to keep the other works in place and act as a retaining wall for the work platform.
This detailed approach means that the water quality and fauna of the Collie River and the riverbanks’ slopes will remain well protected throughout construction and installation of the piles.
Once the necessary structures are in place, our team will methodically remove the backfill material, carefully lift out the bulk-a-bags, retrieve the geofabric and dismantle the sediment fence and silt curtain.
"It was a critical concern of ours to incorporate additional controls in the river front pad construction and amend the methodology to ensure minimal impact on the natural environment." said Alfred Abi Assy, Senior Project Engineer. "Slope stability and erosion protection were key objectives in the design of the temporary works and we are proud of the solution that was designed and implemented."
Page last reviewed: | Last updated: