Onslow Road Upgrade

We upgraded 76 km of road to reduce travel times and improve safety in the Pilbara. Stage 2 works began in September 2019.
Onslow Road <em>Upgrade</em>

Overview 

Onslow Road, south of Twitchin Road, carries about 240 vehicles per day, of which 30 per cent are heavy vehicles, while at the intersection with North West Coastal Highway, the traffic count rises to 550 vehicles per day (30 per cent heavy vehicles).

This project improves overall safety and traffic efficiency in the area. It was completed in two stages.

Stage 1 was completed in April 2019. It is a 33 km stretch on the south east end included:

  • Upgrading the North West Coastal Highway and Onslow Road intersection.

Stage 2 was 43 km long and includes:

  • Structural overlay and resealing
  • Targeted sub-base and sub-grade improvements
  • Replacement and extension of existing culverts
  • Upgrades to signage and road markings

April 2019

Stage one completed

March 2020

Stage two completed

Acknowledgement of country

The Government of Western Australia acknowledges the traditional custodians throughout Western Australia and their continuing connection to the land, waters and community. We pay our respects to all members of the Aboriginal communities and their cultures; and to Elders both past and present.

Tell us what you think

Help us improve our website by sharing your thoughts and suggestions.

Provide feedback