In April 2014, we identified significant structural deficiencies requiring attention on Bridge 0782 on Roberts Street in Moora.

Works required included the demolition of the existing deteriorated structural components and timber/concrete overlay and construction of a new reinforced concrete structural deck.

Minor works included wing wall repairs and extensions, pile repairs, stringers replacement and corrosion protection.

Work has been completed and the bridge was officially opened on 4 August 2017.

 

 