Ravensthorpe Heavy Haulage Route

Overview

In response to community concerns about safety on South Coast Highway through Ravensthorpe, Main Roads WA undertook a planning study to consider alignment options for a heavy vehicle route around the town site.

As an outcome of this study and community consultation, a preferred alignment has been selected and funding allocated to construct the project.

South Coast Highway, which has operated as a significant freight route for many years, climbs steeply through Ravensthorpe.

Most heavy vehicles climb the Ravensthorpe Hill without incident. However, a small minority fail to negotiate the steep grade and stall on the hill. The local community and stakeholders have become increasingly concerned with the regularity of these incidents and the risks associated with the recovery of these vehicles.

Livestock vehicles also spill effluent on the road as they climb the hill, making the road slippery and reducing town site amenity.

Traffic on the road network in the Ravensthorpe area is increasing due to growth in the local mining and agriculture sectors. A significant number of these vehicles are double road trains, carting grain and other agricultural products such as fertiliser and livestock to and from the Esperance port.

The project also includes the realignment of the intersection of the Hopetoun Road with South Coast Highway as well as undertaking improvements to the main street of Ravensthorpe and associated town entry statements.

 

The alignment definition process

Image: Ravensthrope Heavy Haulage Route Locality Plan 

 

Project schedule

Detailed below are the scheduled timelines for the project from the alignment definition process through to delivery and project closeout.

Construction of the project was delivered in two stages. Stage 1 was the accommodation and pre-construction works. Stage 2 was a Category 2 contract.

 

Approximate Start and Finish Dates​ Tasks​
​February to March 2013 Alignment Definition​
​March 2013 to June 2014 ​Environmental Studies and Clearances
​March to June 2013 ​Heritage Studies
​March to April 2013 ​Noise Studies
​April to December 2013 ​Geometric Designs
​April 2013 to June 2014 ​Land Acquisition (Freehold)
​June 2013 to June 2014 ​Land Acquisition (Unallocated Crown Lanes)
​December 2013 to February 2014 ​Detailed Design
​March to May 2014 ​Preconstruction Works
​March to September 2014 ​Sidetrack Construction
​July 2014 to October 2014 ​Contract Advertisement, Assessment and Award
​November 2014 to July 2015​Construction Works
October to December 2015 ​Construction Works
  

Delivery methodology

The works were delivered using the Category 2 AS 2124 contract methodology. This contracting approach consists of inviting public tenders from pre-qualified contractors who have a demonstrated capability and ability to deliver projects of this scale.

There were opportunities for local suppliers to provide goods and services to the Category 2 contractor required to complete this project.

 

Summary

Funding for the Ravensthorpe Heavy Haulage Route of $20 million was provided to Main Roads over the 2012/13, 2013/14 and 2014/15 financial years. Preconstruction works and sidetrack construction has been completed with an AS2124 contract awarded to NRW Holdings. Construction activities were suspended in July 2015 for the winter months and were resumed end September 2015.

 

Project reference group

A Project Reference Group was established consisting of a Shire of Ravensthorpe representative, Ravensthorpe Shire Council representative, Ravensthorpe Progress Association representative, a community representative and a Main Roads representative. The Reference Group provided the Project Team with information and a link to the local community.

 

What next?

NRW Holdings commenced construction works in January 2015 utilising local Earthworks contractors from Ravensthorpe and surrounding towns. Good progress was made with embankment construction activities. Pavement stabilisation began 2 November and finished by 20 November with the sealing finalised the following day, 21 November. The asphalt began during the first week of December, and signs &guideposts were installed during December. The heavy haulage route was officially opened by the Minister for Transport on Monday 21 December 2015 with only very minor works to be finalised beyond Christmas. The improvements to the main street through Ravensthorpe will be undertaken by the local shire and are yet to be finalised.

 

Further information

Please contact Susie Chapman, Community Engagement Manager on 9892 0555.

 
Modified: 06 Jan 2016