ROAD WORKS ON GREAT EASTERN HIGHWAY KELLERBERRIN
Main Roads Western Australia and ALine East advise of road works on Great Eastern Highway at Kellerberrin which will affect operators of oversize loads.
PERIOD
Drainage works will commence on Tuesday 27 October 2009, with completion expected by mid December 2009.
The daily working hours are 07:00 hours to 18:00 hours, including weekends.
CONDITIONS
Lane closures will be in place intermittently and contra-flow configuration will be implemented.
Traffic control and speed restrictions will be in place both during and after the scheduled work hours.
The available lane width during these works is 4.0 metres with traffic management in place.
Operators of oversize loads wider than 4.0 metres must:
- contact the site at least 24 hours prior to their proposed move, to ensure that their load can be accommodated;
- have a minimum ground clearance of at least 1.2 metres.
CONTACT
ALine East – Michael Young, Construction Manager on 0437 700 239; or
ALine East – Travis Wagland, Site Supervisor on 0429 377 718.
CANCELLATION
This HVO Update will self-cancel when the works are complete.
Dennis O’Reilly
Acting Director Heavy Vehicle Operations
22 October 2009