ROADWORKS ON WEST COAST HIGHWAY, SCARBOROUGH
Main Roads Western Australia advises of road and footpath construction works on West Coast Highway between Scarborough Beach Road and Manning Street in Scarborough.
PERIOD
Works will commence on Monday 21 September 2009 with completion expected by the end of December 2009.
The working hours are 07:00 hrs to 17:00 hrs including weekends.
CONDITIONS
Lane closures will be in place intermittently and contra-flow configuration will be implemented.
The available lane width during these works is 3.5 metres with traffic management in place.
Operators of oversize loads wider than 3.5 metres must contact the site at least 24 hours prior to their proposed move, to ensure that their load can be accommodated.
CONTACT
Highway Construction – Daniel Harrison 0409 005 459 or Aaron Jobbins 0439 527 011.
CANCELLATION
This HVO Update will self-cancel when the works are complete.
Doug Morgan
Director Heavy Vehicle Operations
3 September 2009